KENNEDY SPACE CENTER, FLA. --  Reflected in the water of the Banana River is Space Shuttle Atlantis, sitting on Launch Pad 39A.  Atlantis rolled out to the pad for the second time before dawn.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Ken Thornsley
KSC-07pd1204
KENNEDY SPACE CENTER, FLA. --   Viewed across an arm of the Banana River, Space Shuttle Atlantis sits on Launch Pad 39A.  At right of the pad is the 300,000-gallon water tower that provides the water for sound suppression during liftoff.  Atlantis rolled out to the pad for the second time before dawn.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Ken Thornsley
KSC-07pd1201
KENNEDY SPACE CENTER, FLA. --  Space Shuttle Atlantis, mounted on a mobile launch platform, finally rests on the hard stand of Launch Pad 39A after an early morning rollout.  This is the second rollout for the shuttle. Seen on either side of the main engine exhaust hole on the launcher platform are the tail service masts. Their function is to provide umbilical connections for liquid oxygen and liquid hydrogen lines to fuel the external tank from storage tanks adjacent to the launch pad. Other umbilical lines carry helium and nitrogen, as well as ground electrical power and connections for vehicle data and communications. First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1200
KENNEDY SPACE CENTER, FLA. --   Space Shuttle Atlantis, mounted on a mobile launch platform, finally rests on the hard stand of Launch Pad 39A, straddling the flame trench. This is the second rollout for the shuttle.  The flame trench transecting the pad's mound at ground level is 490 feet long, 58 feet wide and 40 feet high. It is made of concrete and refractory brick. Pad structures are insulated from the intense heat of launch by the flame deflector system, which protects the flame trench floor and the pad surface along the top of the flame trench.  On the left of the shuttle are the fixed service structure and rotating service structure in open position.  When closed, the rotating structure provides protected access to the orbiter for changeout and servicing of payloads at the pad. It is supported by a rotating bridge that pivots about a vertical axis on the west side of the pad's flame trench.  The white area in the center is the Payload Changeout Room, an enclosed, environmentally controlled portion of the rotating service structure that supports payload delivery at the launch pad and subsequent vertical installation in the orbiter payload bay.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1199
KENNEDY SPACE CENTER, FLA. --  Under a feather-painted sky, Space Shuttle Atlantis, mounted on a mobile launch platform atop a crawler transporter, creeps up the ramp to Launch Pad 39A.  This is the second rollout for the shuttle.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1196
KENNEDY SPACE CENTER, FLA. --   From a vantage point across scrub lands and the Banana River, Space Shuttle Atlantis is seen finally sitting on Launch Pad 39A.  Atlantis rolled out to the pad for the second time before dawn.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Ken Thornsley
KSC-07pd1203
KENNEDY SPACE CENTER, FLA. --   The locomotive and rail cars carrying solid rocket booster motor segments and two aft exit cone segments roll past the Vehicle Assembly Building to the Rotation, Processing and Surge Facility (RPSF) in Kennedy Space Center's Launch Complex 39 Area.  The RPSF is used for solid rocket motor receiving, rotation and inspection, and supports aft booster buildup.  When live solid rocket motor segments arrive at the processing facility, they  are positioned under one of the cranes. Handling slings are then attached to and remove the railcar cover. The segment is inspected while it remains horizontal.  The two overhead cranes hoist the segment, rotate it to a vertical position and place it on a fixed stand. The aft handling ring is then removed. The segment is hoisted again and lowered onto a transportation and storage pallet, and the forward handling ring is removed to allow inspections. It is then transported to one of the surge buildings and temporarily stored until it is needed for booster stacking in the VAB.  While enroute, solid rocket motor segments were involved in a derailment in Alabama.  The rail cars carrying these segments remained upright and were undamaged.  An inspection determined these segment cars could continue on to Florida.  The segments themselves will undergo further evaluation at Kennedy before they are cleared for flight.  Other segments involved in the derailment will be returned to a plant in Utah for further evaluation.  Photo credit: NASA/George Shelton
KSC-07pd1208
KENNEDY SPACE CENTER, FLA. --   The final rail car carrying solid rocket booster motor segments moves its cargo into the Rotation, Processing and Surge Facility (RPSF) in Kennedy Space Center's Launch Complex 39 Area. The RPSF is used for solid rocket motor receiving, rotation and inspection, and supports aft booster buildup.  When live solid rocket motor segments arrive at the processing facility, they  are positioned under one of the cranes. Handling slings are then attached to and remove the railcar cover. The segment is inspected while it remains horizontal.  The two overhead cranes hoist the segment, rotate it to a vertical position and place it on a fixed stand. The aft handling ring is then removed. The segment is hoisted again and lowered onto a transportation and storage pallet, and the forward handling ring is removed to allow inspections. It is then transported to one of the surge buildings and temporarily stored until it is needed for booster stacking in the VAB.  While enroute, solid rocket motor segments were involved in a derailment in Alabama.  The rail cars carrying these segments remained upright and were undamaged.  An inspection determined these segment cars could continue on to Florida.  The segments themselves will undergo further evaluation at Kennedy before they are cleared for flight.  Other segments involved in the derailment will be returned to a plant in Utah for further evaluation.  Photo credit: NASA/George Shelton
KSC-07pd1211
KENNEDY SPACE CENTER, FLA. --  An alligator, seen just above the shrubs, has a close-up view of Space Shuttle Atlantis as it sits on Launch Pad 39A. Atlantis rolled out to the pad before dawn for the second time.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Ken Thornsley
KSC-07pd1205
KENNEDY SPACE CENTER, FLA. --   The locomotive and rail cars carrying solid rocket booster motor segments and two aft exit cone segments roll toward the Rotation, Processing and Surge Facility (RPSF) in Kennedy Space Center's Launch Complex 39 Area.   The RPSF is used for solid rocket motor receiving, rotation and inspection, and supports aft booster buildup.  When live solid rocket motor segments arrive at the processing facility, they  are positioned under one of the cranes. Handling slings are then attached to and remove the railcar cover. The segment is inspected while it remains horizontal.  The two overhead cranes hoist the segment, rotate it to a vertical position and place it on a fixed stand. The aft handling ring is then removed. The segment is hoisted again and lowered onto a transportation and storage pallet, and the forward handling ring is removed to allow inspections. It is then transported to one of the surge buildings and temporarily stored until it is needed for booster stacking in the VAB.  While enroute, solid rocket motor segments were involved in a derailment in Alabama.  The rail cars carrying these segments remained upright and were undamaged.  An inspection determined these segment cars could continue on to Florida.  The segments themselves will undergo further evaluation at Kennedy before they are cleared for flight.  Other segments involved in the derailment will be returned to a plant in Utah for further evaluation.  Photo credit: NASA_George Shelton
KSC-07pd-1209
KENNEDY SPACE CENTER, FLA. --    The locomotive and rail cars carrying solid rocket booster motor segments and two aft exit cone segments roll to the Rotation, Processing and Surge Facility in Kennedy Space Center's Launch Complex 39 Area.  The main facility is used for solid rocket motor receiving, rotation and inspection, and supports aft booster buildup.  When live solid rocket motor segments arrive at the processing facility, they  are positioned under one of the cranes. Handling slings are then attached to and remove the railcar cover. The segment is inspected while it remains horizontal.  The two overhead cranes hoist the segment, rotate it to a vertical position and place it on a fixed stand. The aft handling ring is then removed. The segment is hoisted again and lowered onto a transportation and storage pallet, and the forward handling ring is removed to allow inspections. It is then transported to one of the surge buildings and temporarily stored until it is needed for booster stacking in the VAB.  While enroute, solid rocket motor segments were involved in a derailment in Alabama.  The rail cars carrying these segments remained upright and were undamaged.  An inspection determined these segment cars could continue on to Florida.  The segments themselves will undergo further evaluation at Kennedy before they are cleared for flight.  Other segments involved in the derailment will be returned to a plant in Utah for further evaluation.  Photo credit: NASA/George Shelton
KSC-07pd1206
KENNEDY SPACE CENTER, FLA. --  The leading edge of the mobile launch platform atop a crawler transporter, and carrying Space Shuttle Atlantis, heads toward the gate of Launch Pad 39A.  This is the second rollout for the shuttle.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1195
KENNEDY SPACE CENTER, FLA. --   Space Shuttle Atlantis, mounted on a mobile launch platform, finally rests next to the fixed service structure on the hard stand of Launch Pad 39A after an early morning rollout.  Seen at the top of the service structure is the 80-foot-tall lightning mast.  Atlantis rolled out to the pad for the second time before dawn.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Ken Thornsley
KSC-07pd1202
KENNEDY SPACE CENTER, FLA. --  Reflected in water in a drainage canal, Space Shuttle Atlantis, mounted on a mobile launch platform atop a crawler transporter, heads for Launch Pad 39A.  This is the second rollout for the shuttle.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1194
KENNEDY SPACE CENTER, FLA. --   The locomotive and rail cars carrying solid rocket booster motor segments and two aft exit cone segments roll to the Rotation, Processing and Surge Facility (RPSF) in Kennedy Space Center's Launch Complex 39 Area.  In the background, at left, is the Vehicle Assembly Building.  The RPSF is used for solid rocket motor receiving, rotation and inspection, and supports aft booster buildup.  When live solid rocket motor segments arrive at the processing facility, they  are positioned under one of the cranes. Handling slings are then attached to and remove the railcar cover. The segment is inspected while it remains horizontal.  The two overhead cranes hoist the segment, rotate it to a vertical position and place it on a fixed stand. The aft handling ring is then removed. The segment is hoisted again and lowered onto a transportation and storage pallet, and the forward handling ring is removed to allow inspections. It is then transported to one of the surge buildings and temporarily stored until it is needed for booster stacking in the VAB.  While enroute, solid rocket motor segments were involved in a derailment in Alabama.  The rail cars carrying these segments remained upright and were undamaged.  An inspection determined these segment cars could continue on to Florida.  The segments themselves will undergo further evaluation at Kennedy before they are cleared for flight.  Other segments involved in the derailment will be returned to a plant in Utah for further evaluation.  Photo credit: NASA/George Shelton
KSC-07pd1207
KENNEDY SPACE CENTER, FLA. --   The locomotive and rail cars carrying solid rocket booster motor segments and two aft exit cone segments deliver their cargo to the Rotation, Processing and Surge Facility (RPSF) in Kennedy Space Center's Launch Complex 39 Area.  The RPSF is used for solid rocket motor receiving, rotation and inspection, and supports aft booster buildup.  When live solid rocket motor segments arrive at the processing facility, they  are positioned under one of the cranes. Handling slings are then attached to and remove the railcar cover. The segment is inspected while it remains horizontal.  The two overhead cranes hoist the segment, rotate it to a vertical position and place it on a fixed stand. The aft handling ring is then removed. The segment is hoisted again and lowered onto a transportation and storage pallet, and the forward handling ring is removed to allow inspections. It is then transported to one of the surge buildings and temporarily stored until it is needed for booster stacking in the VAB.  While enroute, solid rocket motor segments were involved in a derailment in Alabama.  The rail cars carrying these segments remained upright and were undamaged.  An inspection determined these segment cars could continue on to Florida.  The segments themselves will undergo further evaluation at Kennedy before they are cleared for flight.  Other segments involved in the derailment will be returned to a plant in Utah for further evaluation.  Photo credit: NASA/George Shelton
KSC-07pd1210
KENNEDY SPACE CENTER, FLA. --   This view of Space Shuttle Atlantis, mounted on a mobile launch platform, as it moves onto Launch Pad 39A also shows the expendable rocket launch pads in the background on the east side of the Banana River. This is the second rollout for the shuttle.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1197
KENNEDY SPACE CENTER, FLA. --    Space Shuttle Atlantis, mounted on a mobile launch platform, finally rests on the hard stand of Launch Pad 39A.   At bottom left is the White Room, which is situated on the end of the fixed service structure's orbiter access arm.  At the top of the photo, in the background, is the Atlantic Ocean.   This is the second rollout for the shuttle.  First motion out of the Vehicle Assembly Building was at 5:02 a.m. EDT. In late February, while Atlantis was on the launch pad, Atlantis' external tank received hail damage during a severe thunderstorm that passed through the Kennedy Space Center Launch Complex 39 area. The hail caused visible divots in the giant tank's foam insulation, as well as minor surface damage to about 26 heat shield tiles on the shuttle's left wing. The shuttle was returned to the VAB for repairs. The launch of Space Shuttle Atlantis on mission STS-117 is now targeted for June 8. A flight readiness review will be held on May 30 and 31.  Photo credit: NASA/Troy Cryder
KSC-07pd1198
Space Shuttle Atlantis (STS-135) is seen atop the Mobile Launch Platform (MLP) during its journey from High Bay 3 in the Vehicle Assembly Building to Launch Pad 39a for its final flight, Tuesday evening, May 31, 2011, at Kennedy Space Center in Cape Canaveral, Fla. The 3.4-mile trek, known as "rollout," will take about seven hours to complete. Atlantis will carry the Raffaello multipurpose logistics module to deliver supplies, logistics and spare parts to the International Space Station. The launch of STS-135 is targeted for July 8. Photo Credit: (NASA/Bill Ingalls)
Atlantis STS-135 Rollout
Space Shuttle Atlantis (STS-135) is seen atop the Mobile Launch Platform (MLP) during its journey from High Bay 3 in the Vehicle Assembly Building to Launch Pad 39a for its final flight, Tuesday evening, May 31, 2011, at Kennedy Space Center in Cape Canaveral, Fla. The 3.4-mile trek, known as "rollout," will take about seven hours to complete. Atlantis will carry the Raffaello multipurpose logistics module to deliver supplies, logistics and spare parts to the International Space Station. The launch of STS-135 is targeted for July 8. Photo Credit: (NASA/Bill Ingalls)
Atlantis STS-135 Rollout
Space Shuttle Atlantis (STS-135) is seen atop the Mobile Launch Platform (MLP) during its journey from High Bay 3 in the Vehicle Assembly Building to Launch Pad 39a for its final flight, Tuesday evening, May 31, 2011, at Kennedy Space Center in Cape Canaveral, Fla. The 3.4-mile trek, known as "rollout," will take about seven hours to complete. Atlantis will carry the Raffaello multipurpose logistics module to deliver supplies, logistics and spare parts to the International Space Station. The launch of STS-135 is targeted for July 8. Photo Credit: (NASA/Bill Ingalls)
Atlantis STS-135 Rollout